1. Overview¶
This is a screen that summarizes the types and progress of jobs registered in the project.
2. Work history¶
Work history This is a screen showing all the changes that have occurred in the project.
3. Work¶
Jobs registered in the project can be searched according to conditions.
Search criteria can be added in the 'Add search criteria' column.
Search conditions are added as follows.
4. Time Required¶
This is a screen that shows the details of the revision of the 'time required' of the job.- Record the'time required' in the work.

- Check the details of the modified time required. Search conditions use is same as how to use the search conditions in the 'Work' menu.

5. Gantt Chart¶
Check the progress of the job registered in the project with the Gantt chart.
The default unit is Week, if you want to see it in days, keep clicking on 'Zoom In'.
You can check the daily Gantt chart as shown below.
6. Calendar¶
You can check the progress of work on the calendar. Please refer to the legend on the calendar.
7. Wiki¶
Wiki pages are provided for each project. Please check the page below for the syntax of the wiki article
Redmine wiki article